After three months of planning the excavator turned up this morning. Two big threes are now gone and the surface layer will be removed tomorrow. That means that drilling and blasting could be done by the end of the week. The timing was perfect since the building permit popped into my inbox this afternoon!

If everything goes as planned (and it better! ) I should have the foundation done by next saturday, and then the workshop turns up the following monday. As mentioned earlier it comes as a pre-fab building, so hopefully it’ll be roofed and ready for internal work in about 14 days. Fantastic!